Plan at rail level and plan at the lower part of the towers, of Britannia Bridge. Text to say that this is a drawing from contract number 10, with signatures

May 1846

1 drawing on 2 sheets. Working drawing for the Britannia Bridge showing elevation of inscription of the Frieze on the Abutment Tower Carnarvon side. Inscription reads "ERECTED ANNO DOMINI MDCCCXLIX ROBERT STEPHENSON ENGINEER"

[1846-1848]

1 drawing on 1 sheet. Working drawing of the Britannia Bridge showing the plan of Shore Tower at A & B

06 July 1848

Drawing No. 5 for Contract No. 10 Britannia Bridge. Drawing is of longitudinal section of one of the middle towers. This is the drawing No. 5 as referred to in the "Contract No. 10 Britannia Bridge Contract" the day made and entered into by us with the Chester and Holyhead Railway Company. Signed by Benjamin [T] Nowell, John Hemingway, J B Hemingway and Charles Pearson

May 1846

2 drawings on 1 sheet. Working drawing of the Britannia Bridge showing sections of temple finish for the Middle and Shore Towers

[1848]

2 drawings on 1 sheet. Working drawing of the Britannia Bridge showing front elevation and side elevation of tower and winged wall

February 1848

1 drawing on 2 sheets. Working drawing for the Britannia Bridge showing elevation of Bridge.

February 1848 - March 1848

Three drawings on one sheet. Drawing No. 8 for Contract No. 10 Britannia Bridge. First drawing is of end towers at entrance of tunnel on Caernarvon side, second drawing is of front elevation, third drawing is of longitudinal section. This is the drawing No. 8 as referred to in the "Contract No. 10 Britannia Bridge Contract" the day made and entered into by us with the Chester and Holyhead Railway Company. Signed by Benjamin [T] Nowell, John Hemingway, J B Hemingway and Charles Pearson

May 1846

5 drawings on 1 sheet. Working drawing of the Britannia Bridge showing sections, plan of tower and elevation of rear of tower

23 February 1848

2 drawings on 1 sheet. Working drawing of the Britannia Bridge showing general plan of level of the tube and general plan of high water level

[1846-1848]

Drawing No. 4 for Contract No. 10 Britannia Bridge. Drawing is of a side elevation of one of the middle towers. This is the drawing No. 4 as referred to in the "Contract No. 10 Britannia Bridge Contract" the day made and entered into by us with the Chester and Holyhead Railway Company. Signed by Benjamin [T] Nowell, John Hemingway, J B Hemingway and Charles Pearson

May 1846

Two drawings on one sheet of end tower and wing wall Anglesea side. Drawing No. 10 for Contract No. 10 Britannia Bridge. First drawing is of transverse section of wing, second drawing is of elevation of end tower and wing. This is the drawing No. 10 as referred to in the "Contract No. 10 Britannia Bridge Contract" the day made and entered into by us with the Chester and Holyhead Railway Company. Signed by Benjamin [T] Nowell, John Hemingway, J B Hemingway and Charles Pearson

May 1846

2 drawings on 1 sheet. Working drawing of the Britannia Bridge showing section on the line A-B and profile

01 March 1848

1 drawing on 1 sheet. Working drawing of the Britannia Bridge showing section of temple finish for the Centre Towers

[1848]

Four drawings on one sheet. Drawing No. 6 for Contract No. 10 Britannia Bridge. First drawing is of plan at letter b, second drawing is of plan at letter c, third drawing is of plan at letter a, fourth drawing is of plan at letter d. This is the drawing No. 6 as referred to in the "Contract No. 10 Britannia Bridge Contract" the day made and entered into by us with the Chester and Holyhead Railway Company. Signed by Benjamin [T] Nowell, John Hemingway, J B Hemingway and Charles Pearson.

May 1846

1 drawing on 1 sheet. Working drawing for the Britannia Bridge showing side elevation of temple finishing Shore Towers

06 July 1848

1 drawing on 1 sheet. Working drawing of the Britannia Bridge showing sketches of sections of the Shore Tower

21 January 1848

2 drawings on 1 sheet. Working drawing for the Britannia Bridge showing front and side elevations of Shore Tower Carnarvon Side. Annotations relating to work on the girders, temple finishings, filling in of the recesses and a note referencing Robert Stephenson

01 March 1847