041 - Great Western Railway Contract 1S

Object Type: Folder
In Folder: Historical Engineering Collection


View Gallery

Title
Description
Date

Details of Culverts. Twelve drawings on one sheet. Drawings one to three are of sections at A.B, drawings four to six are of sections at C.D, drawings seven to nine are of elevations, drawings ten to twelve are of plans.

1839-1841

Details of culverts. Twelve drawings on one sheet. Drawings one to three are of longitudinal section at A.B, drawings four to six are of transverse section at C.D, drawings seven to nine are of elevations, drawings ten to twelve are of plans.

17 September 1839

Details of Bridge No. 1 West Hendred. Six drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at A.B, third drawing is of sections at G.H.I, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of longitudinal section at C.D, sixth drawing is of back elevation at E.F.

17 September 1839

Details of bridge over canal at Ardington including requirements for brickwork, stone and iron. Five drawings on one sheet. First drawing is of elevation, second drawing is of section at C.D, third drawing is of transverse section at A.B, fourth drawing is of plan of superstructure and plan of foundations, fifth drawing is of transverse section at G.H.

17 September 1839

Details of Bridge. Five drawings on one sheet. First drawing is of elevation, second drawing is of section on line C.D, third drawing is of section on line A.B, fourth drawing Is of plan of superstructure and plan of foundations, fifth drawing is of section on line G.H. Signed by Isambard Kingdom Brunel and Edward Jackson.

17 September 1839

Details of bridge at Milton. Eight drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at A.B, third drawing is of sections at E, F and G, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of transverse section, sixth drawing is of elevation and longitudinal section, seventh drawing is of longitudinal section at C.D, eighth drawing is of plan.

1839-1841

One drawing on sheet showing cross section of contract no. 1S from parish of Ardington to parish Dudcot.

17 September 1839

Details of Milton Bridge. Eight drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at A.B, third drawing is of sections at E, F and G, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of transverse section, sixth drawing is of elevation and longitudinal section, seventh drawing is of longitudinal section at C.D, eighth drawing is of plan.

1839-1841

Details of Bridge. Eight drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at C.D, third drawing is of sections at E, F and G, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of transverse section, sixth drawing is of elevation and longitudinal section, seventh drawing is of longitudinal section at A.B, eighth drawing is of plan. Signed by Isambard Kingdom Brunel and Edward Jackson.

17 September 1839

One drawing on sheet showing plan of contract no. 1S from parish of Ardington to parish Dudcot passing through Steventon.

17 September 1839

Details of cutting and embankment. Two drawings on one sheet. First drawing is of cutting, second drawing is of embankment. Signed by Isambard Kingdom Brunel and Edward Jackson.

17 September 1839

Details of Culverts. Twelve drawings on one sheet. Drawings one to three are of longitudinal sections at A.B, drawings four to six are of transverse sections at C.D, drawings seven to nine are of elevations, drawings ten to twelve are of plans. Signed by Isambard Kingdom Brunel and Edward Jackson.

[1839-1841]

Details of 6ft culvert at West Locking and No.6 at Ardington. Four drawings on one sheet. First drawing is of longitudinal section at A.B, second drawing is of elevation, third drawing is of transverse section at C.D, fourth drawing is of plan. Signed by Isambard Kingdom Brunel and Edward Jackson.

17 September 1839

Details of the bridge over the canal at Ardington including a report on the status of the works being carried out as of 20th July 1840. Three drawings on sheet. First drawing is of sections, second drawing is of elevation, third drawing is of plan of superstructure and plan of foundations.

March 1840

Details of Bridge. Six drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at A.B, third drawing is of sections at C, D and E, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of longitudinal section at F.G, sixth drawing is of back elevation at H.I. Signed by Isambard Kingdom Brunel and Edward Jackson.

17 September 1839

Details of bridge No.1 West Hendred. Six drawings on one sheet. First drawing is of elevation, second drawing is of transverse section at A.B, third drawing is of sections at G.H.I, fourth drawing is of plan of foundations and plan of superstructure, fifth drawing is of longitudinal section at C.D, sixth drawing is of back elevation.

1835-1845

Details of cutting and embankment. Two drawings on one sheet. First drawing is of cutting, second drawing is of embankment.

17 September 1839