021 - Great Western Railway Contract 3B Extension

Object Type: Folder
In Folder: Historical Engineering Collection


View Gallery

Title
Description
Date

Plan at road line of the pier at the south west and north east corners of the bridge. Working drawing, right hand side is torn. Stamped with McIntosh v G.W.R.C. Defendants Documents. Stamped with McIntosh v G.W.R.C. Defendants Documents.

no date, circa 1836-1840

Unidentified drawings of sections of [cross sections of land.] Stamped with McIntosh v G.W.R.C. Defendants Documents.

1839-1840

Details of east entrance of Twerton Long Tunnel. Drawing is of elevation of East Front of Twerton Tunnel with hand written calculations. Stamped with McIntosh v G.W.R.C. Defendants Documents.

1839-1840

Drawings of Cross Post Gate Bridge: section at Doundations, plan of the top of wall, section at level of rails and sections of returning walls. Stamped with McIntosh v G.W.R.C. Defendants Documents. Stamped with McIntosh v G.W.R.C. Defendants Documents.

8th May 1839

Contract Level Book 1, page 10, taken and plotted by T C Bell, with dimensions and workings out in pencil.

6th February 1838

Details of West Entrance to Twerton Long Tunnel. Two drawings on one sheet. Drawing No. 4 for contract No. 3B Extension for Twerton Tunnel. First drawing of west front of Twerton Tunnel. Second drawing of transverse section at AB.

1836-1840

Contract Level Book 1, page 11, taken and plotted by T C Bell, with dimensions and workings out in pencil.

6th February 1838

Details of Pennyquick Brook Culvert. Four drawings on one sheet. Working drawing No. 4 for Contract No. 3B Extension. First drawing is of an elevation, second drawing is of transverse section at CD, third drawing is of plan, fourth drawing is of longitudinal section at AB. Stamped with McIntosh v G.W.R.C. defendants Documents.

1836-1840

Three sketches on one sheet. First drawing is of plan of line, second drawing is of cap for newel of X post bridge, third drawing unidentified. Stamped with McIntosh v G.W.R.C. Defendants Documents.

1836-1840

Cross section in cutting and cross section in Embankment

24th October 1837

Details of culvert for Pennyquick Brook. Four drawings on one sheet. Drawings on contract No. 3B Extension for Twerton Tunnel. First drawing of elevation, second drawing of transverse section at CD, third drawing of plan, fourth drawing of longitudinal section at AB.

1836-1840

Drawing of gradients with copy letter relating to construction dated June 1839 and Jan 1840. Stamped with McIntosh v G.W.R.C. Defendants Documents.

10 January 1840

Cross section of Twerton Long Tunnel. Drawing No. 6 for Contract No. 3B Extension. Elevation of part of Twerton Tunnel. Stamped with McIntosh v G.W.R.C. defendants Documents.

1836-1840

Details of the portal of Twerton Long Tunnel. Four drawings on one sheet. Drawing No, 4 for Contract No. 3B Extension. First drawing is of elevation, second drawing is of transverse section at CD, third drawing is of transverse section at EF, fourth drawing is of plan at AB. Stamped with McIntosh v G.W.R.C. defendants Documents.

1836-1840

Drawing of centre line of intended diversion of Lane No. 12 Newton St. Loe. Stamped with McIntosh v G.W.R.C. Defendants Documents.

1836-1840

Back elevation of the entrance to Twerton Long Tunnel. Three drawings on one sheet. Drawing No, 4A for Contract No, 3B Extension. First drawing is of back elevation, second drawing is of transverse section at GH, third drawing is of plan at IK. Stamped with McIntosh v G.W.R.C. defendants Documents.

1836-1839

Details of Cutting and Embankment. Two drawings on one sheet. Drawing No. 2 for Contract No. 3B Extension. First drawing is of a cutting, second drawing is of an embankment. Stamped with McIntosh v G.W.R.C. defendants Documents.

1846-1840

Front Elevation of Twerton Long Tunnel. Four drawings on one sheet. Drawing No. 4 for contract No. 3B Extension for Twerton Tunnel. First drawing of front elevation, second drawing of section at CD and third drawing of section at EF, fourth drawing of plan at AB.

1836-1839